^ Back to Top

A24: Walls up to First Floor Height

Thursday, January 19, 2012

Most walls are up to full first floor height, electrical sockets/ switches being positioned.

 

A24: Erecting Rebar, Pouring Footings

Saturday, December 31, 2011

Rebar structure going up, foundations and footings being concreted in.

 

A24: Walls Going Up

Friday, December 23, 2011

Most foundations and footings under concrete, work started on walls.

 

A24: First Blocks Laid

Monday, December 12, 2011

Most foundation trenches and footings dug. First blocks being laid.

 

A24: Rebar, Footings and Foundations Trenches

Saturday, November 26, 2011

Piles of rebar have been prepared and work is well advanced with the footing excavations and foundation trenches.

 

A24: Breaking Ground, Digging Footings

Sunday, November 20, 2011

Grid layed out and ground broken. Manually digging footings.

 

A24: Preparing Building Grid

Sunday, November 13, 2011

Service quarters pad raised to the same level as the main house pad. Driveway prepared with compacted sub-grade. Building grid being prepared prior to starting work excavating foundation trenches & footings.

 

A24: Building Pad Complete, Bending Rebar

Monday, November 07, 2011

Building pad is complete, bending rebar continues

 

A24: Raising Level, Preparing Rebar

Saturday, October 29, 2011

The heavy rains have passed and work has resumed. The level of the building pad is been raised with heavy grade compacted rubble. Steel rebar is being prepared.

 

A24: Site Fill and Compacting Subbase

Sunday, October 16, 2011

Bad weather this week has hampered progress. Workers haven't been able to arrive and the ground has been too wet to use heavy machinery. Some fill has been delivered & compacted.

 

B6: Handmade Cabinets, Pool Patio, Painting

Sunday, October 09, 2011

All sliding doors/windows, interior doors and cabinets are installed. Interior of guest house painted, likewise ceilings in main house.

 

A24: Clearing Lot and Preparing Terrace

Saturday, October 08, 2011

The lot has been cleared where necessary and work is underway excavating sand to prepare a compacted rubble & subbase building pad.

 

G11: Project Complete

Friday, October 07, 2011

The project was finished a few months ago, but the curtains only went up last week. So here are the photos of the completed, furnished home.

 

F1: Swimming Pool and Painting Ceilings

Friday, October 07, 2011

The replacement window panes finally arrived and have been installed. The house has been cleaned top to bottom and painting of ceilings has started. All cabinets installed.

 

B6: Krombeplast Windows from Casa Nova, Managua

Tuesday, July 26, 2011

Double glazed Krombeplast windows arrive all the way from sunny Vladivostok via Guatemala and Casa Nova, Managua. Installation almost complete 5 days after delivery.

 

F1: Installing Aluver Aluminium Windows Part 4

Tuesday, July 26, 2011

All windows now installed, just waiting for replacements from breakages to arrive. Kitchen bar built. Site generally cleared up. The light at the end of the tunnel is blurring into view...

 

F1: Installing Aluver Aluminium Windows Part 3

Friday, July 15, 2011

Just a few profiles remain to be installed and more than half the panes are now in. Corner mitered floor to ceiling windows in upstairs bedrooms. Mosquito screens due to arrive this week. Driveway area taking shape.

 

B6: Swimming Pool Rebar and Formwork Complete

Friday, July 15, 2011

Steel rebar and form work complete for the swimming pool and swimming pool light in position. Work has begun pouring concrete for swimming pool walls.

 

F1: Installing Aluver Aluminium Windows Part 2

Sunday, July 03, 2011

Most small and medium sized window profiles installed and some panes are in. Floor tracks cut and ready for large window profiles. Kitchen marble counter tops and cabinets almost ready.

 

B6: Swimming Pool Rebar Part 2

Sunday, July 03, 2011

Swimming pool rebar for base and steps done, just the walls now remain. Gypsum PermaBase walls for internal and external closets, including surf board closet.

 
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. Next page