Roof timbers still going up in the main house. Sheet rock partition walls finished and base coat of paint applied in the service quarters.
Most roof timbers prepared, ridge beam hoisted into position in the main house. Service quarters floor and shower tiling complete.
Service quarters - sheet rock wall partitions being built and floor tiling started. Main house - fine parge finished and roof timber preparations continue.
Smooth parge coat almost complete. Galvanised steel roof on. Roof terrace parapet being built using insulated concrete.
Anti corrosive painting of steel roof girders complete and galvanised steel roof sheeting going on. Upstairs walls complete and getting parged.
Fine parge and piedra laja being applied to ground floor walls. Rough parge on 2nd floor walls. Steel roof frame almost complete and being painted with anti corrosive.
Fine parge complete in service quarters. Rough parge still in progress in the main house. Concrete floors going down & timber roof beams going up in main house.
The service quarters are almost ready for painting. Parging continues on the rest of the house. Timber being prepared for roof beams.
Most second floor walls are up. Parging interior and exterior walls. Steel frame for roof almost ready. Rebar for roof garden retainer.
Grey work for the service quarters is being finished off. Main house walls being parged. Timbers being prepared for main house roof.
Work continues with the second floor walls. A start has been made on the steel roof frame.
The roof is on the service quarters and work is underway parging the walls for the main house. Roof timbers are being prepared for the main house roof.
Second floor concrete pouring is complete and work is now continuing with the upstairs rebar structure and walls
Timber and steel frame roof going up over the service quarters. The terrace section uses a timber frame, while a metal frame is being used for the roof over the inside area.
All second floor rebar is down and tubing for electrical cables and water pipes is in place. Concrete has been poured for about a third of the upstairs area.
Concrete has been poured for the floor of the service quarters. Final bits of block work being finished off in the main house.
Most of the rebar is now laid for the second floor and the majority of the tubing for water and electric cables are down.
The final bit of block work is getting finished off above the lintels, the forms for the terrace arches are being removed, work has started on steel frame for roof.
Walls and girders with structural tubing support steel rebar strengthened concrete floor. Work is currently underway laying the rebar.
All the walls are up to full height. Formwork is up and has been filled for the pool side terrace arches.
Heavy gauge steel girders hoisted into place in preparation for second floor.
The majority of the walls are up to their full height and most lintels are done. Some interesting formwork going on in preparation for the archways on the pool side terrace.
The concrete has been poured for the stairs and all the walls are up to the level of the first floor.
Arched lintels are being constructed over many internal doorways, and at the service quarters terrace. The main sewer line (PVC) is being laid.
Most of the block work for the first floor is complete and preparations are underway for the second floor. Formwork and rebar for stairs is complete and ready for pouring.
Block work well advanced, but this being a two floor house there's plenty left to do. Rebar structure for stairs started.
Some walls are now reaching their full height. PVC electrical conduits getting embedded in concrete walls. PVC water pipes on site.
Most of the rebar structure is in place and a lot of cement has been poured into the foundations. Block work for walls has started at the southern end of the house.
Service quarters walls almost finished. A lot of progress has been made on the main house walls over the past 10 days.
Work progresses on the steel rebar foundations & structure. The first walls for the main house are now in process. The service quarters square pillars are being replaced with round ones.