Construction progress reports from within the Nicaragua area

 

A24: Roof Structure and Stuccoing

Steel roof frame going up over ground floor. First floor walls nearing full height. Walls getting stuccoed.

A24: First Floor Form Removed

Formwork used to support the first floor slab has been removed.

A24: First Floor Slab Poured and Walls Going Up

First floor slab poured and work now progressing with the upstairs walls. Stairs also poured. Work is advancing with the domestic water circuit.

A24: Concrete Rebar Spiral Staircase 2

Rebar bent and laid for spiral staircase. Double reinforced grid complete. Ready to pour slab.

A24: Concrete Rebar Spiral Staircase

Form in place for concrete rebar spiral staircase. Double layer of reinforcement going down for first floor slab.

A24: Preparing Formwork for First Floor Slab

Work moving along quickly getting form in place for first floor slab.

A24: Preparing First Floor Rebar

First floor rebar preparations continue and work underway getting the form in place for pouring first floor slab.

A24: Preparring For Second Floor

All walls up to first floor height. Preparing form for second floor and front balcony.

A24: Walls up to First Floor Height

Most walls are up to full first floor height, electrical sockets/ switches being positioned.

A24: Walls Going Up

Most foundations and footings under concrete, work started on walls.

A24: First Blocks Laid

Most foundation trenches and footings dug. First blocks being laid.

A24: Erecting Rebar, Pouring Footings

Rebar structure going up, foundations and footings being concreted in.

A24: Rebar, Footings and Foundations Trenches

Piles of rebar have been prepared and work is well advanced with the footing excavations and foundation trenches.

A24: Breaking Ground, Digging Footings

Grid layed out and ground broken. Manually digging footings.

A24: Preparing Building Grid

Service quarters pad raised to the same level as the main house pad. Driveway prepared with compacted sub-grade. Building grid being prepared prior to starting work excavating foundation trenches & footings.

A24: Building Pad Complete, Bending Rebar

Building pad is complete, bending rebar continues

A24: Raising Level, Preparing Rebar

The heavy rains have passed and work has resumed. The level of the building pad is been raised with heavy grade compacted rubble. Steel rebar is being prepared.

A24: Site Fill and Compacting Subbase

Bad weather this week has hampered progress. Workers haven't been able to arrive and the ground has been too wet to use heavy machinery. Some fill has been delivered & compacted.

A24: Clearing Lot and Preparing Terrace

The lot has been cleared where necessary and work is underway excavating sand to prepare a compacted rubble & subbase building pad.

F1: Swimming Pool and Painting Ceilings

The replacement window panes finally arrived and have been installed. The house has been cleaned top to bottom and painting of ceilings has started. All cabinets installed.

B6: Handmade Cabinets, Pool Patio, Painting

All sliding doors/windows, interior doors and cabinets are installed. Interior of guest house painted, likewise ceilings in main house.

G11: Project Complete

The project was finished a few months ago, but the curtains only went up last week. So here are the photos of the completed, furnished home.

F1: Installing Aluver Aluminium Windows Part 4

All windows now installed, just waiting for replacements from breakages to arrive. Kitchen bar built. Site generally cleared up. The light at the end of the tunnel is blurring into view...

B6: Krombeplast Windows from Casa Nova, Managua

Double glazed Krombeplast windows arrive all the way from sunny Vladivostok via Guatemala and Casa Nova, Managua. Installation almost complete 5 days after delivery.

F1: Installing Aluver Aluminium Windows Part 3

Just a few profiles remain to be installed and more than half the panes are now in. Corner mitered floor to ceiling windows in upstairs bedrooms. Mosquito screens due to arrive this week. Driveway area taking shape.

B6: Swimming Pool Rebar and Formwork Complete

Steel rebar and form work complete for the swimming pool and swimming pool light in position. Work has begun pouring concrete for swimming pool walls.

F1: Installing Aluver Aluminium Windows Part 2

Most small and medium sized window profiles installed and some panes are in. Floor tracks cut and ready for large window profiles. Kitchen marble counter tops and cabinets almost ready.

B6: Swimming Pool Rebar Part 2

Swimming pool rebar for base and steps done, just the walls now remain. Gypsum PermaBase walls for internal and external closets, including surf board closet.

F1: Installing Aluver Aluminum Window Part 1

Assembling window frames and cutting tracks in tiled concrete floors to reduce height of the base profile above surrounding floor. Steel rails painted.

F1: Aluver Windows Arrive From Guatemala

Shipment of double glazed Aluver windows arrived from Guatemala. Roof on service quarters/ garage. Cabinet installation continues. Steel railings going up.