Construction progress reports from within the Nicaragua area

 

D1: Three Stage Biodegrading Septic System

Septic tank excavation dug and first three tanks in place. Fourth tank on site. Getting this done before the rains arrive in next month and water table rises. Walls advancing quickly, reaching first floor height.

I1: Soil Cement

Cement reinforced soil beneath what will be the front terrace. 18 sacks of cement spread around this area, watered in then manually re-compacted. Rebar being erected. Walls going up.

I1: Digging Foundation Trenches, Footings.

Foundation trenches and footings being dug out. Steel rods being prepared into beam cages for rebar structure. First footings and columns down.

D1: Walls Going Up

Walls going up, waves out front going OFF!

I1: Grid up, Preparing Rebar Footings

Grid is up around the building pad. First delivery of steel rebar on site. Work underway preparing footings. Some footing excavations have been dug on ocean side of project.

D1: Foundations and footings down, Walls going up

Most footings and foundations under concrete, walls going up.

D1: Erecting Rebar, Pouring Footings, Transformer

Lots of activity this past week. Transformer has been installed, most foundation trenches/ footing excavations are dug, first rebar columns have been erected and some footings have been poured.

D1: Foundation Trenches & Footing Excavations

Work underway digging foundation trenches and footing excavations. First deliveries of steel on site and rebar columns being prepared.

I1: Compacted Subbase Pad - Complete

Building pad complete. Ready to put up grid, draw out foundations and get the pick-axe squad to work on the foundation trenches and footings excavations.

I1: Raising Pad and Compacting

Work proceeds raising the level of the building pad up to the height of the brow at the beach end of the property. A thick fill is necessary as the site has a pronounced dip where the main house is sited.

D1: Compacted Subbase Terraces Complete

Terraces for main house and garage complete, builders shed is up, electric supply is ready. Some work done on excavation for beachfront swimming pool.

I1: Staking out the Property

Access to the building area has been cleared. Staking out the footprint of the construction.

D1: Raising and Compacting pad

Main building and garage pad being raised and compacted.

D1: Compacted Subbase Terrace 1

Some sand has been excavated and refilled with rubble.

D1: Clearing Site Part 1

The site has been cleared where necessary. Work will soon begin excavating sand before refilling with rubble and compacting.

A24: Kohler Generator and Transfer Installed

Generator and auto transfer installed. Double pane PVC window frames being installed. Cabinetry, door-frames and interior doors being installed. Work started on beach shower and steps.

A24: Kohler LPG Generator, Automatic Transfer

Kohler LPG generator and automatic transfer delivered. Cabinets on site. Roof on beach rancho. Pool tiling half complete.

A24: Wrought Iron Gates, Rails delivered

Wrought iron gates and rails delivered. Form work removed from swimming pool. Pool patio tiling underway. Finishing off terrace tiling. Driveway.

A24: Swimming Pool Poured and Form Removed

Concrete has been poured for the swimming pool. Holes dug for pool gazebo footings. Piedra Laja work on turret complete. Built in balcony BBQ underway.

A24: Floor Tiling 3, Swimming Pool Formwork

Most walls primed and floor tiling almost complete. Swimming pool rebar complete, floor poured and form up for walls. Domestic water tank in place.

A24: Floor Tiling 2, Swimming Pool Rebar 1

Floor tiling well underway and work has begun prepping rebar for the swimming pool. Septic tanks which were delivered last week are in place and connected.

A24: Enclosed Eaves, Floor Tiling 1

Floor tiling started with first few laid on the stardeck. Work continues enclosing eaves. Ceiling work complete except for in master suite. Steel staircase from beach level to balcony underway.

A24: Beach Retaining Wall 2, Ceiling Panels

Floor tiles on-site, ceiling grid complete and approx half gypsum ceiling panels up. Work underway enclosing eaves. Floors being readied for tiling. Metal spiral staircase from ground to first floor.

A24: Beach Retaining Wall 1, Ceiling Grid

Work continues hanging aluminum ceiling grid, tiling roof and rounding off corners. Foundations for concrete block beach retaining wall.

A24: Tiling Roof, Hanging Ceiling Grid

Roof tile going on, ceiling grid being hung and corners being snubbed. Fine stucco being finished off.

A24: Running electric cables, Fine stucco

Fine stucco complete. Roof structure complete over 1st floor and galvanized tin sheets going up. A/c tubing and electric cables in place and awaiting installation of units.

A24: Cupola Slab, First Floor Roof Structure

Cupola slab has been poured. Steel roof structure going up over first floor. Copper tubing and electric cabling being embedded in walls for air conditioning.

A24: Cupola Rebar Complete

Cupola rebar is complete and ready to advance with slab. Running electric cables between circuit panels and outlets. Galvanized tin sheets going on steel roof frame.

A24: Cupola Rebar and Roof Frame 3

Cupola form is complete and cupola rebar work underway. First floor water tubing getting connected to ground floor. Ground floor being refilled & compacted ready for concreting.

A24: Cupola Form and Roof Frame 2

Work continues with the roof frame, stuccoing walls, running electric cabling and water pipes. Slab done for star deck. Form made for cupola dome.